Q 1.Find the Payback period for the following project: Project X Initial Outlay $8,150 Year 1 $3,250 Year 2 $3,890 Year 3 $3,820 Year 4 $6,100 The answer should be calculated to two decimal places. 2.Find the Payback period for the following project: Project Y Initial Outlay $18,100 Year 1 $5,360 Year 2 $5,700 Year 3 $5,690 Year 4 $7,040 The answer should be calculated to two decimal places. 3.Find the Discounted Payback period for the following project. The discount rate is 9% Project X Initial Outlay $8,770 Year 1 $3,189 Year 2 $3,564 Year 3 $5,029 Year 4 $7,352 Round the answer to two decimal places. 4.Find the Discounted Payback period for the following project. The discount rate is 9% Project X Initial Outlay $17,832 Year 1 $5,392 Year 2 $5,784 Year 3 $5,583 Year 4 $8,273 Round the answer to two decimal places.